# 04-03 Monday
- Draft html outline
- Chen
- Collect relevant images or other information important to the project
- Together?
- Create & populate JSON file
- Together?
# 04-04 Tuesday
- Finish basic Javascript
- Maybe each of us can create a particular section of the code to work on?
- for instance, Melissa works on the #house-bar, Michael works on submit form, Chen works on drop-down function?
- Or if we have 2-hour work session: 1 hour working independently and 1 hour work together with the driver/navigator system
- Create super simple css so that the page looks clean
- Chen will look into the basic css
# 04-05 Wednesday
- Finalize MVP
- The goal is to have all the functionality working, even if it looks super simple;
- So that we can improve the codes and make it prettier later while not breaking the code
# 04-06 Thursday
- Refracting Javascript
- Edit CSS so that the page looks prettier
# 04-07 Friday
- Final Testing
# Basic Guideline
- Whenever work on a new feature (such as additional functionality), do so on a new local branch
- Discuss together before merging
- Commit regularly, name each commit concisely and meaningfully by starting with a verb
- such as 'add eventlistener to submit button' etc.