Implement Registry Multi-tenancy with Cognito in the loop #185
Comments
📆 April Status: Completion date expected to be delayed 1 week due to technology comparison needed. No impact on other tasks or deliveries |
📆 May status: Delayed 1 sprint due to increase in scope and complexity. Solution has been identified and is underway. Slack built into schedule should alleviate delays. No impact on delivery expected. |
📆 June status: Delayed an additional sprint due to increasing scope and learning-on-the-fly with OpenSearch authorization. No impact on build anticipated. |
📆 July status: Long delay due to Registry / API issues causing block in #179. Full deployment with authorization layer to be delayed, but partial deployment expected by delivery date. This delivery will actually cause less impact on users, so the partial deployment will have no effect on success of delivery. |
📆 August status: Working this architecture and deployment with MCP SAs. Expected completion by end of month. |
📆 September status: tightly coupled with NASA-PDS/planetary-data-cloud#35, this is in work. Continuing to work issues with serverless approach and AWS team. |
📆 October Status: tightly coupled with NASA-PDS/planetary-data-cloud#35, this is in work, but blocked by AWS technical team response times and issues being encountered with the service |
📆 04/2024 status: Delayed an additional 2 sprints. Will require separate mini-I&T to complete this delivery and release. |
📆 05/2024 status: Delayed 1 additional sprint. Will require separate mini-I&T to complete this delivery and release. Outside of scope of B14.1 delivery. |
📆 06/2024 status: Delayed an additional sprint due to additional unforeseen blocking issues. Significant impacts on rest of tasks in Build. All impacts will be review with SWG. |
📆 07/2024 status: Progress ongoing, but delayed an additional 2 sprints due to additional unforeseen blocking issues with networking. Significant impacts on rest of tasks in Build. All impacts will be reviewed with SWG. |
📆 08/2024 status: Progress ongoing, but delayed an additional sprint. To be done by end of this sprint |
This is done. Moving remaining sub-tasks to next build since they are some wrap-up activities that are not required for delivery to production. |
💡 Description
Initial design and Serverless, schema setup:
OpenSearch Serverless Authentication
Tools adaptations
Loader Tools
API
Sweeper
Other
Additional Testing
Deployment and Data Migration
Cutover planning
The text was updated successfully, but these errors were encountered: