A Lot usually generates a contract, which in turn has an expected duration. |
Beta Was this translation helpful? Give feedback.
-
How would it be for a DPS where you naturally have many contracts per lot? Or how about mini-tenders for FA? |
Beta Was this translation helpful? Give feedback.
-
Sorry, probably I was not able to express myself correctly. I am not suggesting to remove the property. I am just suggesting that a better naming can be possible, that can represent what is included in the current definition for that property; that is, the fact that it is an estimated starting date. |
Beta Was this translation helpful? Give feedback.
-
@ec-mcs In the DPS we track:
|
Beta Was this translation helpful? Give feedback.
-
The properties between Contract, Lot and Period need to be reviewed since the predicates do not make sense in some cases. For example, in "Contract hasEvaluationDuration Period", and other... (contracts are not evaluated, but lots are). Other issues with these properties may also exist. |
Beta Was this translation helpful? Give feedback.
-
At the moment, there is a relation from Contract to Duration, epo:hasEstimatedDuration: The definition for this relations was changed to |
Beta Was this translation helpful? Give feedback.
-
If the definication is indicating a Contract has an estimated Duration the reuse of this predicate is not possible. |
Beta Was this translation helpful? Give feedback.
-
@muricna Should we also change the name of the predicate to epo:hasContractEstimatedDuration? |
Beta Was this translation helpful? Give feedback.
-
If it is at ContractTerm level I am not sure it is need in the contract |
Beta Was this translation helpful? Give feedback.
-
I was analysing the OWL restriction file (version 2.0.1) for opening possible issues in case of strange things noticed.
My attention was caught by the property hasContractDuration between the Lot and the Period. The definition is "The estimated date when the contract is to be started."
Question: why is it called hasContractDuration if it is a property for the Lot? Shouldn't be for the Contract a property called hasContractDuration?
In the name of the property the fact that is estimated is not captured. In addition it is a date, not a period, according to the definition.
If we stick to the definition, something like hasContractEstimatedStartingDate seems more inline (which i s a xsd:date not a period).
What do you think about it?