The Waterfall
graph is a nice way to represent some values on a bar chart, together with other values that add up to their difference. A typical use would be breaking incomes or expenses into pieces. Since a picture is worth a thousand word, make sure to have a look at the demo. It can be used as follows:
var Waterfall = require('paths/waterfall');
var waterfall = Waterfall({
data: [
{
name: 'Gross income',
value: 30,
absolute: true
}
{
name: 'Transport',
value: -6
}
{
name: 'Distribution',
value: -3
}
{
name: 'Detail income'
absolute: true
}
{
name: 'Taxes',
value: -8
}
{
name: 'Net income'
absolute: true
}
],
compute: {
color: function(i, item) {
if (item.absolute) return 'green';
else return 'red';
}
},
width: 500,
height: 400,
gutter: 10
});
Parameters:
-
width
,height
: have the obvious geometric meaning -
data
: contains an array with the data to plot. The precise form of the data is not important, because the actual value of the data will be extracted by theaccessor
function. -
accessor
: a function that is applied to each datum inside each item indata
to extract its value. It should return an object with either theabsolute
orvalue
property, or both.value
represents the height of the current bar.absolute
should betrue
if the bar should stand on its own, rather than appearing as the difference between consecutive bars. -
max
,min
(optional): maximum and minimum values represented on the chart. They are computed if they are not given explicitly, but setting them explicitly can be useful to draw more than one chart on the same scale. -
gutter
(optional, default = 10): the space to leave between each bar -
compute
(optional): see the introduction.
The first item in the waterfall chart should have the value
property and absolute
set to true
. The subsequent bars will usually have either value
or absolute
but not both. If they have value
, this is considered relative to the previous bar. If they have absolute
set to true
, the value will be computed by summing all relative values up to that point.
For instance, the height of Detail income
in the example is 21 = 30 - 6 - 3
, while the height of Net income
is 13 = 21 - 8
.
The object returned by the Waterfall
function contains the curves
array, on which one can iterate to draw the rectangles. Each member of this array has the properties line
, index
, value
and item
, the latter containing the actual datum associated to the rectangle. value
instead contains the height computed for this rectangle: it coincides with item.value
whenever this is present, and otherwise it is equal to the cumulative value computed. For instance, value
would be 21
for the Detail Income
rectangle in the example above.