Issue Description
As we discussed in Meeting #4 project plan should be transferred to ProjectLibre. I will transfer whole project plan. Addition to that, plan will extended to the last day of the semester. For this part of the task, I will be working with @mbatuhancelik .
Step Details
Steps that will be performed:
Final Actions
When the whole work is done, it can be reviewed from here.
Deadline of the Issue
31.10.2022 - Monday - 23.59
Reviewer
Altay Acar
Deadline for the Review
01.10.2022 - Tuesday - 15.00