Hi everyone,
I’m running some tests with Frepple and working on a resource that has a particular constraint: to be cost-effective, it must be used for a minimum number of continuous hours due to the high costs associated with starting it up (1 hour of heating) and cleaning it. Therefore, we need to accumulate manufacturing orders before activating it, as it cannot be used indiscriminately. How should I parameterize this type of resource in the system to ensure that it is scheduled only when the required production minimums are met, optimizing its profitability?
Thanks in advance for your help!