/imp |
Important dates for the team, and work left for SAR (System Acceptance Review) |
Agrim Gupta |
SAR_Plan |
19/1/2018 |
20 Jan
: All fourthies and thirdies MUST attend. Optional for sophies.- Will conclude on what exactly we need to show for the SAR video.
- Start making the report for all what has been done till now
- Also start working on bodyworks and get a fix on them before
25 Jan
. Try to have bodyworks for the arm as well.
- Batteries are limited till Kadar Bhai comes. Use them judicially.
- Order 60A roboclaw by
23 Jan
- Get a fix on how to charge BMS by
1 Feb
- Start making the report for all what has been done till now
- Level 3 hardware implementation:
19,20,21 Jan
- Attempt at level 4 on the small bot over Republic day Weekend
- Attempt at level 4 on the rover post
4 Feb
- Fix on the experiments to be done by
21 Jan
- Start doing and shooting (so as to save time later) experiments as and when you do. Try and complete experiments side by
31 Jan
- Bio sensor integration to be done by
7 Feb
- IMPORTANT Order SCiO by
25 Jan
- SCiO tests to be done from
7 Feb-14 Feb
- Report making time from
14 Feb
onwards.
- Finish basic video collection of Arm+Rover by
30 Jan
. - Finish basic video collection of BioAssembly+Rover by
4 Feb
. - Will keep
4 Feb -> 14 Feb
to achieve stretch goals for the team, namely:- Mechanical: Bad terrain traversal near lake side
- Arm: IK control
- Autonomous: Leddar implementation for Level 4
- BioSc: SCiO integration with rover and live tests of it with rover
Exact days to shoot on to be discussed in
20 Jan
meet