This timeline shows when all of the tasks in the task list should be completed, as well as when we will have finished major milestones.

Task # Task Description Start Date End Date
11 Research distributed computing project architecture 11-15-18 12-15-18
21 Research executing arbitrary code in browser 11-15-18 12-15-18
25 Investigate incentives for volunteers 11-15-18 12-15-18
1 Develop Master infrastructure 12-15-18 12-22-18
3 Implement API for accepting projects 12-23-18 01-12-19
2 Design scheduling system for assigning workers to projects 12-23-18 01-12-19
x Milestone: worker makes requests for work from master
4 Develop system for automatically deploying projects 12-23-18 01-12-19
x Milestone: master server accepts project requests
x Milestone: master server accepts worker requests
5 Test master service functionality 01-13-19 01-16-19
6 Document instructions for use 01-17-19 01-18-19
31 Design interface for managing sending and accepting data 01-19-19 01-25-19
32 Design interface for tracking progress on tasks 01-19-19 01-25-19
33 Design interface for managing worker assignments 01-19-19 01-25-19
x Milestone: interface documentation completed
34 Create boilerplate projects in Node.js, Python, Java 01-26-19 01-30-19
x Milestone: standard library completed in multiple languages
12 Create a sample project 01-31-19 02-07-19
13 Design sample project data model 02-08-19 02-18-19
x Milestone: project server communicates project status to master
14 Design sample project worker scheduling algorithm 02-08-19 02-18-19
x Milestone: sample project created and documented
23 Create worker node for sample project 02-08-19 02-18-19
x Milestone: worker executes assigned work and reports progress
22 Verify performance characteristics of worker nodes 02-19-19 03-01-19
15 Test project service funcionality 02-18-19 03-01-19
24 Test worker functionality 02-18-19 03-01-19
x Milestone: all testing completed