This repository is used for automated reporting on development work and for maintenance of dev/design documentation and reporting site for the Center for Digital Humanities at Princeton Development and Design Team.

github pages

reporting

GitHub Actions are used to collect data on releases (via repository tags) and issues closed, with points and velocity (based on GitHub and ZenHub APIs). The data files created by these scripts are used for reporting in the Hugo site.

hugo site

The dev/design site is generated with Hugo using the Docsy theme. The Hugo site is automatically compiled from the main branch and published to gh-pages.

prerequisites

Hugo requires the following to be installed locally:

  • go
  • hugo
  • node

All can be installed using brew.

setup

This site uses the docsy theme, which is installed as a go module. Modules can be installed or updated by runnning:

hugo mod get

Install npm dependencies:

npm install

And run locally:

hugo server -D

Creating iteration reports

Update iteration definitions as needed in iterations.json if you need to add the dates for the next iteration (although these will likely be populated ahead of time now that we are using that data file for quarterly development schedule).

Pull the latest changes from GitHub to get data added by the issue collection and iteration summary GitHub Action scripts, which run on Saturdays.

Create a new iteration report using the iteration report page bundle archetype with the filename for the post you want to create. By convention, use isodates for iteration reports. To autogenerate for the current date, use this command:

hugo new --kind iteration-report blog/iteration-reports/`date +'%Y-%m-%d'`

The iteration report archetype assumes it is run on the first day of the new iteration; previous iteration start is calculated accordingly, and should be edited when necessary. Make sure the iteration_start date matches the iteration start value in the iterations summary data file, and update the post title to reflect the iteration dates.

Edit the new post to add content and any demo or featured content, then commit and push to GitHub to publish.

Creating quarterly dev schedule

Create a new post under content/blog, set layout to quarterlyschedule_v2 and configure date range start and end in page parameters, e.g.::

layout: quarterlyschedule_v2
date_range:
    start: "2023-10-01"
    end: "2024-01-15"

Update the iterations.json data file to add the dates for all iterations during the time period you want to cover (best to go slightly beyond the range when possible).

Version 2 of our quarterly schedule aims to track the bigger picture of our full portfolio and the work taking place at all phases of a project, not only active development. The information in the iteration file should be structured as a dictionary or mapping of projects with a list of status codes relevant for that iteration, e.g.:

"work": {
    "risk": ["writing"],
    "geotaste": ["data", "code", "writing"],
    "geniza": ["consulting"],
    "startwords": ["paused"],
    "ppa": ["data", "planning"]
}

Statuses in the iteration data file are converted to emojis using the mapping in the projects data file; when you add a new status, add a new emoji.

There is also a list of inactive statuses (currently only paused, :paused:) which should not be counted when determining if a project is active or partially active in any given iteration.

Previous quarterly dev schedule format

For each iteration, add:

  • projects: the list of projects projected to be active that iteration
  • partial: optional, list of projects that are in planning or wrap up phases
  • notes: optional; dictionary with list of notes per project for display in the schedule; when two notes are displayed, the second will be displayed the second week of the iteration.

Be sure to add project colors and partial colors to _quarterly_schedule.scss when you add new projects to the schedule.

Iterations may be a variable number of weeks; they are typically two, but one and two week iterations are supported by the layout. To include a non-iteration week or time period on the calendar, add the property "skip" to the iteration definition. To display a label on the schedule, add text in a "comment" field. For example:

    {
        "from": "2021-06-28",
        "to": "2021-07-02",
        "comment": "R&D week",
        "skip": "yes"
    }