2021 Sprint 23
Closed Dec 3, 2021
100% complete
2021 Sprint 23 2021.11.16 - 2021.11.29
Retrospective pad: https://pad.riseup.net/p/p-a7pwoTTxZzd1ku7AL2
During this sprint we will continue to work towards our goal of having Zebra act as a fully participating and validating node by the time NU5 activates early 2022. In particular by the end of the Sprint we would like for Zebra to:
- Fully validate Orchar…
2021 Sprint 23 2021.11.16 - 2021.11.29
Retrospective pad: https://pad.riseup.net/p/p-a7pwoTTxZzd1ku7AL2
During this sprint we will continue to work towards our goal of having Zebra act as a fully participating and validating node by the time NU5 activates early 2022. In particular by the end of the Sprint we would like for Zebra to:
- Fully validate Orchard, Sapling and Sprout proofs, note commitment trees & anchors,
- Validate miner subsidies and fees
- Validate lock times
- Implement ZIP-203 for transaction expiry
- Close existing connections to outdated peers after a network upgrade activation