4.7.1 Milestone Plan #2354

Closed
25 tasks done
bmicklea opened this issue Sep 6, 2016 · 0 comments
Closed
25 tasks done

4.7.1 Milestone Plan #2354

bmicklea opened this issue Sep 6, 2016 · 0 comments
Labels
kind/planning A checklist of issues for planning a particular sprint.
Milestone

Comments

@bmicklea
Copy link

bmicklea commented Sep 6, 2016

Milestone Overview

This is a bug fix release.

For more information about our development process please see our development process page.

Schedule

This release will be an Eclipse-signed release.

  • Code complete milestone: target September 7
  • GitHub release complete (QA verified) milestone: target September 8
  • Release shipped milestone: target September 9

Schedule Detail

Code complete milestone

  • Milestone issues complete
  • Smoke tests started

Release candidate created milestone

  • Release candidate created
  • Test cycles started
  • Release notes created
  • Docs complete

GitHub release complete (QA verified) milestone

  • Release completed and QA verified
  • Final release information updated on GitHub
  • Docs reviewed and live

Eclipse signed release complete (IP verified) milestone

  • Release signing submitted to Eclipse Foundation (non-blocking)
  • Release updated on codenvy.com (Eclipse Che free cloud offering)
  • Public Factories on codenvy.com QA'ed

Target Milestone Issues

The following issues are targeted for inclusion in the milestone. As issues are closed they are checked. Stretch goals are indicated with "Stretch" before the item.

Epics and Issues

Bugs

@bmicklea bmicklea added the kind/planning A checklist of issues for planning a particular sprint. label Sep 6, 2016
@bmicklea bmicklea added this to the 4.7.1 milestone Sep 6, 2016
@riuvshin riuvshin changed the title 4.7.1 Milestone Plan 4.7.2 Milestone Plan Sep 9, 2016
@riuvshin riuvshin changed the title 4.7.2 Milestone Plan 4.7.1 Milestone Plan Sep 9, 2016
@bmicklea bmicklea closed this as completed Sep 9, 2016
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment
Labels
kind/planning A checklist of issues for planning a particular sprint.
Projects
None yet
Development

No branches or pull requests

1 participant