Level Loading Operations #535

Answered by jdetaeye
RKBusinessAnalyst asked this question in Q&A
Discussion options

You must be logged in to vote

There is no standard feature to achieve this.

With a customization, you can solve it with 2 planning runs: in first planning run you run an capacity unconstrained plan to establish the average load / blue line and generate a capacity calendar for the resources. In a second planning you then run a capacity constrained plan using the average load as the capacity limit.