Level Loading Operations #535
Answered
by
jdetaeye
RKBusinessAnalyst
asked this question in
Q&A
-
Beta Was this translation helpful? Give feedback.
Answered by
jdetaeye
Jul 1, 2022
Replies: 1 comment
-
There is no standard feature to achieve this. With a customization, you can solve it with 2 planning runs: in first planning run you run an capacity unconstrained plan to establish the average load / blue line and generate a capacity calendar for the resources. In a second planning you then run a capacity constrained plan using the average load as the capacity limit. |
Beta Was this translation helpful? Give feedback.
0 replies
Answer selected by
RKBusinessAnalyst
Sign up for free
to join this conversation on GitHub.
Already have an account?
Sign in to comment
There is no standard feature to achieve this.
With a customization, you can solve it with 2 planning runs: in first planning run you run an capacity unconstrained plan to establish the average load / blue line and generate a capacity calendar for the resources. In a second planning you then run a capacity constrained plan using the average load as the capacity limit.