TDSP Tentative Project Plan
jay-mahadeokar edited this page Apr 27, 2011
·
5 revisions
This is a tentative project plan for Implementation of Time Dependent Shortest Path algorithm (TDSP) for pgRouting as per the initial project proposal for Google Summer of Code 2011.
Note - This plan is subject to minor changes as the project proceeds.
26th April - 24th May:
* Study the Boost Graph Library in detail and get accustomed to the data-structures that will
be needed for the implementation of the algorithm.
* Study the Boost Priority Queues Library. Implement the functionality hands on.
* Get fluent with use of git-hub, CMAKE ad other tools required for the development of the project.
* Carry on discussions regarding the design and implementation of the algorithm on the mailing list.
* Come up with different options, use-cases and prototypes for the design of time_dependent_cost
function.
25th May - 5th June:
* Finalize the overall architecture of the project.
* Finalize the database-design\ other storage format which will be used for dynamically
storing\updating the data for time-dependent edge weights.
* Finalize the class-diagram which will be used for the implementation.
* Finalize the prototypes for the SQL-queries and the SQL-shared library functions that must be
implemented.
* Decide the test cases and data that will be needed for rigorous testing of the modules.
* Start coding small trivial modules/functions that will be needed for the project.
6th June - 15th June:
* Implement the basic time-dependent dijkstra algorithm using Boost Graph Library and Boost Priority
Queues Library assuming the time_dependent_cost
* function as black box.
* Test the basic function with dummy data.
16th June - 25th June:
* Implement the shared-library modules needed for retrieving the time-dependent_costs from the database
/ dynamic storage as decided in the design.
26th June - 7th July:
* Implement the SQL queries needed for data retrieval from the database source.
* Implement the SQL queries needed for finding the time dependent edge costs.
* Integrate the basic algorithm and all components using CMAKE scripts.
* Test the basic functionality using dummy data.
7th July - 13th July:
* Prepare and Submit the mid-term evaluation report.
* Work on the code in background.
14th July - 25th July:
* Implement the shared library wrapper functions around the basic function with and without bounding
box limitations.
* Implement any other functions / variants to original functions that may have come up during the brain-
storming period.
* Implement the corresponding SQL queries and write the CMAKE scripts.
26th July - 5th August:
* Test the implementation with test cases and data as planned.
* Fix any bugs / exceptions that come up.
6th August - 16th August:
* Fix any bugs and finish testing.
* Complete the detailed documentation, examples, tutorials regarding the application of the algorithm
in real-world projects.
* Wrap-up any remaining tasks.
* Start working on the final report for the project.
17th August - 22nd August:
* Complete and Submit the final report for the project.