  1. Open complexity: 18
  2. Average time per CP: 2:00
  3. This project time per CP: 3:51
  4. Maximum time per CP: 6:35
  5. Time required: 36:17 - 69:21 - 118:30
  6. Budget required: $1815.00 - $3468.00 - $5925.00
  7. Estimated completion date (1w moving average): Feb. 4, 2014 - Feb. 13, 2014 - Feb. 25, 2014
  8. Time spent: 73:13
  9. Total time budget: 109:30 - 142:34 - 191:43
  10. Total budget: $5475.50 - $7129.00 - $9586.00
  11. Budget limit: $300.00