Skip to content
Alex Vykalyuk edited this page Mar 7, 2014 · 1 revision
  1. Open complexity: 7
  2. Average time per CP: 3:26
  3. This project time per CP: 4:01
  4. Maximum time per CP: 6:35
  5. Time required: 24:02 - 28:12 - 46:05
  6. Budget required: $1202.50 - $1410.50 - $2304.00
  7. Estimated completion date (1w moving average): March 12, 2014 - March 13, 2014 - March 17, 2014
  8. Time spent: 371:31
  9. Total time budget: 395:33 - 399:43 - 417:36
  10. Total budget: $19778.00 - $19986.50 - $20880.00
  11. Budget limit: $10000.00