Skip to content
Alex Vykalyuk edited this page Mar 3, 2014 · 1 revision
  1. Open complexity: 20
  2. Average time per CP: 3:20
  3. This project time per CP: 4:05
  4. Maximum time per CP: 6:35
  5. Time required: 66:47 - 81:57 - 131:40
  6. Budget required: $3339.50 - $4098.00 - $6583.50
  7. Estimated completion date (1w moving average): March 15, 2014 - March 19, 2014 - March 28, 2014
  8. Time spent: 311:58
  9. Total time budget: 378:45 - 393:55 - 443:38
  10. Total budget: $18938.00 - $19696.50 - $22181.50
  11. Budget limit: $10000.00